The next stages include battening out and plaster-boarding the interior. The next major external work will be the building of the outer brick skin of the house. We are all ready to start bricking now, particularly as we have finally got approval for the bricks and the mortar. However, we have been advised that the roof must be loaded first so that the bricks can be tied to the SIPS wall in the finished position (the SIPS will compress slightly when the roof tiles are added). This means that we need to put the slates on the roof first. Unfortunately, we are still waiting for planning approval for these, so this exercise could be delayed a little longer.