Tuesday, 24 April 2018

What happened to Spring?

Our long holiday in Asia with warm/hot and dry weather is over.  We had a great time and hoped that building work would continue apace, but on our return it seems that the UK had not shared in the good weather and it has been decidedly unspringlike.  On the positive side though, it appears that our return has heralded the start of warmer drier weather so although things did not progress well whilst we were away, the builders have really made a difference in the last couple of weeks.
Before we went away, the roofers had started on our Welsh Slates.  When we returned nearly all the roof had been slated, except for the part over the dormer and the location around the chimney.  The section of the dormer cannot be completed until the final solar panels are in place.  The final solar panels cannot be fitted until the dormer window has had its zinc coating.  The zinc man has gone AWOL.  This seems to happen a lot in building!  Anyway, we do think that the slate does look good, but wish that it didn't cost 4 times as much as other good quality slate!

The main roof ridge
The kitchen roof (with inlet and outlet for ventilation & heat recovery system
As soon as we got back, work started on the chimney.  One of our neighbours advised us that jackdaws have a habit of trying to nest in chimneys in the village, so a suitable cage was bought and fitted on top.
  
Finished chimney, awaiting the last few slates
Work has finally started on the external brick wall of the house.  Each morning large tubs of pre-mixed mortar arrive in sufficient quantities to support a day's-worth of bricking.  This is necessary as the colour of the mortar has been specifically agreed with the planning and conservation officers.  The mortar company can supply mortar to a specific colour whereas if it were mixed on site there would be some variations in colour.  Currently nearly all the brickwork for the ground floor has been completed and the scaffolding has been moved further back to allow the brickies to work on the first floor.

Corner of the lounge-diner and the terrace wall

The ground floor wall facing the canal is complete

Internally, all the rooms have had their plasterboard fitted.  Who knew that plasterboard came in different colours?  As well as the usual grey plasterboard, we have pink heat-resistant plasterboard around the wood stove, and green water-resistant plasterboard in the bathrooms.

Pink plasterboard on the left with a smiling 'Jack' 
We currently have 6 plasterers on site, and by the end of today, it is hoped that all the plaster skimming will be completed.



Mixing plaster by the bucket-load

Our bedroom plaster is nearly dry

One corner of the lounge-diner completely dry.

As well as trying to pin down our missing Zinc-man, the next job is to put a 'mist coat' of white paint on all the internal walls.  This is a mix of white emulsion and water.  Following this, the painters get to work and paint most of the walls white.  One or two walls will have 'accent' colours for a bit of variety.
Also, with all the plastering complete, final measurements for the staircase, internal doors and all the windows can now be made and these items put on order.

Since the weather was so good last week, we took the boat out for a few days and met some friends on their boats near Braunston in Northamptonshire.  Before we left, we had to change the gearbox oil as is recommended after 25 hours cruising.  This was a first for us and was a somewhat messy job, but it was successful.  Once we met up near Braunston, a pub became the venue for the reunion.  Leaving the pub in the dark we watched a spectacular lightning show, and just made it back to the boats in time before the thunderstorms hit.  This is the first time we have stayed overnight on 'Charlie Mo' and we found it very comfortable.
Charlie Mo has now done 72 miles on the canals as well as 80 locks.  Not much more cruising will be done until the engine has had its first service which is booked for 10th May.  Since the interval for subsequent services is much longer, later in the summer we are planning to take 'her' further afield.

Leaving Cropredy,

Tranquil Oxford Canal

Land-locked Narrowboat

Lesley honing her driving skills...

...whilst I worked the locks
Since we have no long holidays planned for a while and things are moving a little quicker now, we will endeavour to update the blog slightly more frequently! 

Thursday, 15 March 2018

The wait for Welsh Slate

.....is over!
The slates have been lovingly hewn from the edge of Snowdonia, gently put on to palettes , carefully driven 200 miles to Oxfordshire, and finally expertly unloaded on to our plot!

Definitely not Spanish Slate! 

They do look good, but at 4 times the price of the best Spanish slate, they should do!

There do seem to be a lot of them!
 
Work in progress
A finished section
The slates on the south side of the roof seem to be going on quickly, but gaps have been left for the solar panels to be fitted.  These will be flush with the slates when fitted.  Meanwhile, on the north-facing side, the renewables 'team' are busy finishing off the ventilation system by fitting the intake and outlet vents to the roof.

One vent fitted and waiting for slates

Thursday, 8 March 2018

Fresh air and the Beast from the East

Before the 'Beast from the East' hit us, the plumber managed to finish all the first fix plumbing, but last week, the weather was so cold that all work on the house had to stop and it was not possible to take the boat for another run.  It also meant that our Welsh slates were further delayed as apparently the staff and lorries could not get to the slate quarry, so our chance of the slates arriving this week diminished rapidly.  The canal froze over and was covered in snow.  Although the canal does freeze in the winter, since we are near a lock there is always some water flowing which usually prevents our part of the canal from freezing solid.

Frozen canal, before the snow


4 x 4's only

Even when the canal thawed, we still had snow

Still no work on site

After the thaw at the weekend, the focus moved to one aspect of the 'renewables', namely the Mechanical Ventilation & Heat Recover System (MVHR).  Since the house will be so well sealed it is a requirement to have a ventilation system to make sure that we can get enough air to breath.  In summer, it is easy just to open windows, but in winter opening windows is a really efficient way of losing all the heat.  The MVHR solves this by bringing in fresh air from a vent on the roof and exhausting 'stale' air through another vent.  Normally, the stale air would also take the heat from the house with it, but the 'Heat Recovery' part of the MVHR uses a heat exchanger to transfer the heat from the outgoing air to the incoming air.  This clever bit of kit also takes warmer and more damp air from the bathrooms and the kitchen, dries it, and distributes it to the other rooms.
It does of course mean that a sizeable unit about half the size of a fridge and looking like an oversized lego brick has to be positioned in the void above the downstairs cloakroom, and ducting needs to be fed to all the rooms hidden in the walls and ceilings but avoiding all the newly installed plumbing and cabling, before the plasterboard is fitted.  Currently our bedroom is being used as a storeroom for a significant amount of the ducting and associated materials.


Giant Lego Brick

The bedroom 'Ducting Store'

Hard to believe that all of this will be hidden in the walls and ceilings
Progress is being made, and most of the downstairs has its ducting in place.  Work has now moved on the the more complicated sloping ceilings upstairs.

Ceiling vent in the Study
We have just heard that the slates are on their way and should be at the builder's yard tomorrow.  This is great news as it means that the roofers who were booked for next week can start on Monday.  Their first job will be to batten out the roof and put the felt on it.  This could not be done in advance as the precise size of the slates and the required overlap must be measured when the slates arrive.  Hopefully, the first slates will go on the roof on Tuesday.  Time to set the time-lapse camera up then!

Although we are very pleased with the boat, we have had the boatbuilders down this week to address some of the snags we have come across.  They are making good progress, but there are still a few areas to be looked at.  We have had two sets of friends come to visit this week.  We thought that they wanted to come and see us, but in fact they were only really interested in seeing the boat and possibly the house!

View of the red roof of our boat from the master bedroom.  

I wonder how long we can keep the boat's engine bay this clean?






Wednesday, 21 February 2018

Maiden Voyage

Yesterday's blog covered the delivery and launching of 'Charlie Mo'  We returned to Aynho Wharf this morning to find our boat still tied up where we had left it, and most importantly still afloat with no water where it shouldn't be!  We unpacked some of our 'stuff' and an hour later we set off northwards towards Cropredy.  It is easier to access both sides of the boat from a lock, so we stopped for a short while at a lock to put all the roof furniture in place.  With a further short stop in Banbury, the voyage 'home' took around 6 hours, The drive to the wharf in the morning took about 30 minutes and that was during the Banbury rush hour.   The Oxford Canal is the second busiest canal in the country, only being beaten by the Llangollen Canal.  Throughout the entire voyage we only saw 3 boats on the move, largely due to the fact that it is February, but also locks are closed for maintenance north of Cropredy and south on the Thames.
The log book now has its first entry:  total miles: 10.85, total locks: 8
The ubiquitous time-lapse is at the end.


Aynho Wharf just before setting off

Underway

The first lock

Roof furniture and cratch cover fitted

One of the proud owners

Another lock filling

Celebratory Tesco sandwich and a glass (small for the driver) bubbly

 Timelapse: 10.85 miles and 8 locks in a little under 3 minutes




Tuesday, 20 February 2018

Low Flying Boat

This blog is about the building of our new home in Cropredy.  The village and the plot were chosen because of the Oxford Canal and this gave us the opportunity to own a narrowboat to use in our retirement.  This entry does not cover progress on the house, but does address the delivery of our long-awaited narrowboat.

Our plan was to take delivery of the boat further north nearer the boat-builders, and cruise down to Cropredy, but we are right in the middle of all the winter maintenance stoppages which means that our bit of the canal system is cut off from everywhere else until mid/late March.  We ended up having the boat delivered by low-loader to a canal wharf about 10 miles south of Cropredy.

The transport company were very good at keeping us informed and we arrived at Aynho Wharf a few minutes before the 'first lorry' arrived.  This lorry was a small flat-bed and had a very small crane on-board.  For a while, we were a bit concerned, but it was shortly followed by a much, much larger crane.  The first lorry was only delivering the steel pads that the main crane's outriggers rest on.

Crane with wheels off the ground

After a few minutes the boat arrived on its transport.  It was carefully reversed down the access road and driven forward next to the crane.
First visit to the pub!

Ready for the lift
Strops were fixed around the boat and the lift began.  If was all over in just a few minutes!


Starting the swing

Gently does it!

Nearly there


Just a little more


Floating is a good sign!

One of the boat-builders experts had driven down with the boat and set about setting everything up and giving us a run through of all the controls.  We now have lots of equipment manuals and leaflets to read!

The saloon and bathroon

The Galley

The Saloon and Galley

The Bedroom
Since it was dark when we finished, we left the boat at the wharf.  We will return tomorrow and take the boat on its maiden voyage to Cropredy. . . . . . . . watch this space.

Of course, we just had to set up the timelapse camera to record the 'launch'!













Wednesday, 14 February 2018

Chocolate Surprise

You know how it is: nothing happens for some time, and then everything comes along at once.  Today was such a day.  We turned our backs for a few hours to check the location where the boat is to be 'put in' and to have a meeting with the architects and when we get back the ground floor is a very different place.

Following the installation of the underfloor heating upstairs last week, our builder has finished the jigsaw of insulation pieces for the ground floor sub-floor.  Today was the day that the Underfloor Heating Team were going to come and fit all the pipework and manifolds for the 4 zones of heating downstairs.  They turned up on time and because it is much, much easier to staple the pipes to the insulation boards, rather than fixing to the joist in the ceiling for the upstairs last week, they were done in a few hours.


Making the jigsaw pieces fit

Brief timelapse of the Heating Pipe Installation


The next step is to put the screed down to a depth of 75mm to bring the floor up to, well, floor level!  It was hoped that this would take place on Friday, but because the underfloor pipes were fitted so quickly, our site manager got on the phone and secured it for this afternoon.  By the time we got back to Cropredy, pumping was well underway and we got a quick glimpse of the heating pipes before they were covered.  So we now have a floor which currently looks and feels rather like liquid chocolate, but apparently by tomorrow it will have set hard enough to walk on.


Liquid chocolate by hose, and a brief view of the underfloor heating pipes


Smoothing out

'Tripods' show the required level