Friday 14 September 2018

Broken promises

It's been an erratic week in terms of the house build, with some days having large complement of trades on site, but with one day where only the site manager turned up (and even he went home in disgust)!  It seems that the construction industry is built (sorry for the pun) upon broken promises and unreliability.  Having said that, the 'things to do' list to complete the build is getting shorter.  Even if we do think of things to add to it occasionally, many more things have been crossed off as completed.

The garden is complete.  It 'just' needs a lawn and plants adding to it.  In true builder's fashion, the promised lawn contractor didn't turn up this week either!  Much of the builders rubbish has now been removed.  This was necessary as most of it was on the area designated as driveway and the builders wanted to get on with laying that.  The two unused palettes of bricks were meant to be collected by the supplier (no refund for them, but they would take them back free-of-charge) some weeks ago but they kept on failing to collect them.  They were told that they had until last week to remove them, or they would go with the rubbish to landfill.  A grab-lorry was booked by the builders and yesterday it took the rubbish and the bricks away.  This seems like a real waste, but it is apparently very common in the building industry.  It was inevitable that today, the brick supplier turned up to take the palettes of bricks away.  He didn't stay long!

With the rubbish and bricks removed, or at least relocated elsewhere on the site, the builders set about grading the driveway and putting the foundation stone on it.  We are informed that the official name of this foundation stone is 'MOT type 1'.  This will be covered with decorative gravel hopefully some time next week.  We originally wanted a resin-bonded porous drive, but were advised that we need to wait 12 months to allow the ground to settle first.  In order to avoid the potential for water from the road running into our driveway, we are building a 'hump' out of granite sets.  These will be set into concrete early next week and in order to let the concrete set hard, we won't be able to drive over it for another week.  Fortunately, our long-suffering neighbour is happy to let us leave our car in her large parking area.


Pile of 'MOT-1'

Spread out and compacted

Almost ready for the gravel on top
The paving around the house is now complete and has all been grouted.  It still needs an acid clean to tidy up the edges of the slabs but we are really pleased with it.  For all the problems we have with unreliability and organisation, our builders are capable of doing a good job.

We're not sure if it is a good or bad omen but we had a visit from a pair of swans this week.  It is the first time that we have seen an avian black swan (as opposed to a pub or film!).


Unusual wildlife

Our electrician has not been here as much as we'd like this week, but he has finished the wiring in the garage as well as a lot of smaller jobs in the house.  One of these smaller jobs was to wire up the hot water return pump.  We have never had one of these before and we are really surprised at what a difference it makes.  Our house is fitted with a sort of ring main for hot water.  This small pump continuously pushes hot water around the system which means that when you turn any hot tap on, you get hot water almost instantly and don't have to wait for the hot water to reach you down a long, cold pipe.  So for the cost of running a low power pump, we are saving quite a lot of water.  Whilst on the subject of plumbing, although we have had a toilet in our cloakroom since me moved it, it was finally connected today.

The area around the front door has also progressed this week.  Our feature larch pole has been installed and all the larch cladding in the ceiling completed.  All that is needed now is the fascia boarding and guttering.


Porch area: Work in progress

Almost complete







No comments:

Post a Comment